saascode
climate, energy & agtech·run 110 · May 2026

Queueplot

A renewable EPC scheduling workbench that links each activity and scenario to sourced interconnection-queue events, authority permits, contract milestones, tax-credit assumptions, procurement requirements, resource constraints, commissioning evidence, approvals, and corrections.

Genesis score6.92/10
Make Queueplot real.0/500
500 more votes and Queueplot is authorized for build.
0%500 to authorize
Backing is the vote. When an idea crosses 500, we pull it into the build pipeline and ship it for real — the votes decide what gets built next, not an editor.
The opportunity
1Cross-references
0Inbound connections
0Direct connections
The case

Renewable developers and EPC teams plan around interconnection studies, site control, authority permits, procurement, equipment lead times, tax-credit assumptions, contract obligations, construction, testing, energization, and commercial operation. Generic schedules can store dates without preserving which source, status, dependency, authority, or uncertainty makes each date credible. Queueplot joins the schedule to evidence and scenarios. A public queue row is not an interconnection right, a permit application is not approval, a forecast date is not a commitment, a tax milestone is not qualification, and a generated procurement export is not legal compliance. Source event, planner assumption, contractual milestone, agency acknowledgment, field completion, engineer approval, utility acceptance, tax treatment, procurement decision, and correction remain distinct.

Who pays — and why

A project-controls, development, interconnection, permitting, procurement, tax, construction, or executive leader at a renewable developer or EPC contractor managing a multi-party project schedule.

What it unlocks
A project authority graph preserving legal entity, site, technology, jurisdiction, queue identifier, site control, permits, contracts, tax assumptions, procurement regime, grid operator, authority, utility, EPC parties, owners, and source rights
An evidence-linked schedule where each activity records baseline, forecast, committed date, source, status, uncertainty, predecessor, resource, calendar, owner, approval, external dependency, scenario, actual, variance, and correction
A milestone lifecycle separating application, submission, provider acknowledgment, study or review, decision, contract obligation, field evidence, engineer approval, utility acceptance, placed-in-service or operation claim, tax and procurement review, dispute, and supersession
How Genesis scored it
6.92across seven criteria
tension 7temporal 8blindspot 5buyer 7leverage 8convergence 5why-not 7
8
Temporal window

The source names a June 2026 European procurement date that has now passed; any current obligation must be revalidated rather than treated as future urgency.

8
Asymmetric leverage

Adapters, templates, scenarios, and evidence links can serve many projects once each organization's contracts and calendars are mapped.

5
Convergence

One cross-reference with no inbound or direct connections provides weak corroboration despite the competitive scan.

Why it scored well

A named renewable project-controls buyer, confirmed public grid and regulatory data interfaces, several adjacent orchestration and queue-intelligence products, and no identified Gantt scheduler with native queue evidence and EPC milestone templates support a specific workflow gap.

What's holding it back

The record has only one cross-reference and no inbound or direct connections, one of two source interfaces remained unverified, the original regulatory date has passed, current official applicability needs revalidation, project schedules depend on private contracts and human forecasts, and no structural incumbent cost is shown.

Signals detected5 sources crossed
SignalneuroGrid, Zonevex, Enverus, REplace, Nira, and ContractMotion research

SignalCAISO, PJM, MISO, and ERCOT interface research

SignalFERC eLibrary research

SignalSource-run market scan

SignalTemporal review of supplied claim

Direction briefqueueplot.md
queueplot.md
Want this pointed at your vertical?Point Genesis at your own market and constraints — it invents adjacent, fork-ready ideas, private to you before they hit the public feed.

Discussion

?

No comments yet — be the first to weigh in.